Lancelot Manufacturing is a small textile manufacturer using machinehours as the single indirectcost rate to allocate manufacturing overhead costs to the various jobs contracted during the year. The following estimates are provided for the coming year for the company and for the Case High School band jacket job. Company Case High School Job Direct materials Direct labor Manufacturing overhead costs Machinehours mh mh What is the bid price for the Case High School job if the company uses a ​% markup of total manufacturing​ costs?

Respuesta :

Answer:

$3,927

Explanation:

For the computation of bid price first we need to follow some steps which is shown below:-

Manufacturing overhead rate = Overhead cost ÷ Machine hours

= 45,000 ÷ 100,000

= $0.45

Total manufacturing cost charged to the school

= 2,000 + 400 + (900 × 0.45)

= $2,805

Markup cost = $2,805 × 0.4

= $1,122

Bid price of job = Total manufacturing cost charged to school + Markup cost

= $2,805 + $1,122

= $3,927